Street Surface Maintenance Program - Paving (2013)

Dates 
Construction August - October 2013
Project Status 
Completed
Budget 
$716,122.25
Contact 

Bradley Albert, P.E.
Project Manager
Phone: (503) 786-7609
Fax: (503) 774-8236
Email: albertb@milwaukieoregon.gov

Project Details

 

The 2013 program year of the Street Surface Maintenance Program (SSMP) reconstructed Harrison Street (from Highway 224 to Main Street) and overlaid Main Street (from Scott Street to Washington Street).

 

Alerts & Updates

Last Updated on 2/3/2014

 

All work has been completed. If you have any questions or concerns regarding this project, contact Bradley Albert by phone at (503) 786-7609 or by email at albertb@milwaukieoregon.gov.