- Neighborhoods
-
Community
-
- Overview History Vision Newsroom News Releases Pilot Newsletter Media Contact Projects Volunteer
- Engage Milwaukie Events City Calendar Recreation Biking in Milwaukie Parks and Trails Directory North Clackamas Parks and Recreation Reserve a Room Library
- Schools North Clackamas School District MHS Student of the Month Public Safety Police Clackamas Fire District #1 Code Compliance Emergency Preparedness Emergency Notifications Garbage & Recycling
-
- Business
- Departments
-
Useful Links
-
- Jobs Alerts & Notifications Email Subscriptions Emergency Notifications Meetings City Services A-Z Mapping & GIS
- Contact the City Staff Directory Request a Public Record Report a Code Violation Report a Pothole Report Misconduct Schedule an Inspection Documents & Forms Documents and Reports Forms, Permits, and Applications
- Helpful Links Digital Archives Library Catalog Municipal Code Purchase a Parking Permit Paperless Billing Pay a Ticket or Utility Bill Urban Forest
-
Clay Pipe Replacement Program (2013-2014)
Dates
Construction April 2013 - August 2013
Project Status
Completed
Budget
$1,245,510
Contact
Matthew Palmer
Project Manager
Phone: (503) 786-7602
Fax: (503) 774-8236
Email: palmerm@milwaukieoregon.gov
Project Details
The Clay Pipe Replacement Program was created to ensure of the replacement of the City's in-service Vitrified Clay Pipe (VCP) over a 10 year period. Vitrified Clay Pipes are susceptible to chemical attack at their joints, are brittle, and due to their short lengths and numerous joints are more prone to infiltration. As of 2010, it was estimated that the City had 21,218 feet of VCP in active service.
The 2013-2014 Program Years will focus primarily on replacing VCP on streets that are scheduled to be paved by the Street Surface Maintenance Program (SSMP). These pipe sections will be prioritized for replacement to eliminate the need to replace them later and cut into any newly paved streets.
Alerts & Updates
Last Updated on 12/4/2013
FINAL ACCEPTANCE ISSUED ON 11/18/2013
The Final Acceptance letter was sent to Landis and Landis Construction (LLC) on November 18, 2013. Per the contract, LLC will provide a 1-year warranty on all work performed.