- Neighborhoods
-
Community
-
- Overview History Vision Newsroom News Releases Pilot Newsletter Media Contact Projects Volunteer
- Engage Milwaukie Events City Calendar Recreation Biking in Milwaukie Parks and Trails Directory North Clackamas Parks and Recreation Reserve a Room Library
- Schools North Clackamas School District MHS Student of the Month Public Safety Police Clackamas Fire District #1 Code Compliance Emergency Preparedness Emergency Notifications Garbage & Recycling
-
- Business
- Departments
-
Useful Links
-
- Jobs Alerts & Notifications Email Subscriptions Emergency Notifications Meetings City Services A-Z Mapping & GIS
- Contact the City Staff Directory Request a Public Record Report a Code Violation Report a Pothole Report Misconduct Schedule an Inspection Documents & Forms Documents and Reports Forms, Permits, and Applications
- Helpful Links Digital Archives Library Catalog Municipal Code Purchase a Parking Permit Paperless Billing Pay a Ticket or Utility Bill Urban Forest
-
Grind and Pave 2024
Project Status
Archived
Project Type
Capital Project
Contact
Project Lead:
Benjamin Green, engineering technician 1
503.786.7547
GreenB@milwaukieoregon.gov
Project Details
The project objective is to grind and repave streets that are in poor condition and have been identified by the Public Works Staff, community members, and internal recommendations. The streets selected for this project were evaluated based on their Pavement Condition Index (PCI) along with inspections by city staff. This maintenance project includes the removal of 2 inches of asphalt and the re-installation of 2 inches of new asphalt to provide better quality streets for the community to utilize. Also included in this project is longitudinal striping. This work consists of repainting yellow centerlines and white fog/bike lanes all over Milwaukie.
Project Schedule:
Engineering Phase: January- February 2024
Construction Obligation: June - September 2024
Completion Target Date: September 30th, 2024
Questions? Please contact the project lead, Ben Green, with questions or concerns related to this project.
*Please note that the City of Milwaukie may make modifications to the list of selected streets at any time.
Alerts & Updates
Update 12.04.2024:
Construction complete as of September 2024.
Update 08.20.2024:
The longitudinal striping is complete, and the contractor will begin reinstalling the asphalt berms on Aug. 23.
Update 07.11.2024:
As of July 11, the majority of the paving work is complete with the exception of berm installation on curbless streets and re-installing stop bars and continental crosswalk markings. Due to unforeseen circumstances, SE Where Else Lane will not be paved this summer, but will be prioritized next summer. Residents on Where Else Lane should expect a mailer with additional information.
Crews will begin completing longitudinal striping in the next two months. This work will consist of re-painting yellow center lines and white fog/bike lanes in various locations all over Milwaukie.