International Way Repaving Project

Dates 
June 2012 - July 2012
Project Status 
Completed
Budget 
$1.55 million for all three 2012 Street Surface Maintenance Projects
Contact 

Engineering Department (503) 786-7606

Project Details

The repaving of International Way between 37th Avenue and Harmony Road is planned for June. For the section between 37th Avenue and Freeman Way, contractors will grind away four inches of the road surface within the travel lanes. Areas where the roadway’s base has failed will be reconstructed prior to repaving. Between Freeman and Harmony, damaged base will be repaired and measures will be made to prevent future cracking and the entire paved surface will receive a new two and a half inch overlay. The City will ensure that driveways within this section will be tied in properly.

Alerts & Updates

This project is substantially complete. The contracor will return to fix minor issues prior to final payment.