Lake Road Improvement Project

Dates 
Completed Fall of 2012
Project Status 
Completed
Budget 
$4.3M ($1M coming from City funds since 2008)
Contact 

Engineering Department

Phone: (503) 786-7606

Project Details

The Lake Road Multimodal Improvement Project will construct sidewalks, ADA ramps, 5' bike lanes, a center turn lane, center islands, and stormwater improvements on Lake Road between Guilford Dr. and Where Else Lane.

 

Alerts & Updates

Updated July 18, 2012: Project completed. Contractor working through final punch-list items.