- Neighborhoods
-
Community
-
- Overview History Vision Newsroom News Releases Pilot Newsletter Media Contact Projects Volunteer
- Engage Milwaukie Events City Calendar Recreation Biking in Milwaukie Parks and Trails Directory North Clackamas Parks and Recreation Reserve a Room Library
- Schools North Clackamas School District MHS Student of the Month Public Safety Police Clackamas Fire District #1 Code Compliance Emergency Preparedness Emergency Notifications Garbage & Recycling
-
- Business
- Departments
-
Useful Links
-
- Jobs Alerts & Notifications Email Subscriptions Emergency Notifications Meetings City Services A-Z Mapping & GIS
- Contact the City Staff Directory Request a Public Record Report a Code Violation Report a Pothole Report Misconduct Schedule an Inspection Documents & Forms Documents and Reports Forms, Permits, and Applications
- Helpful Links Digital Archives Library Catalog Municipal Code Purchase a Parking Permit Paperless Billing Pay a Ticket or Utility Bill Urban Forest
-
McLoughlin Blvd (99E) Utility Relocation
Dates
January 2017 - April 2017
Project Status
Completed
Budget
$813,853
Contact
Rick Buen, PE
Project Manager
Phone: 503-786-7602
Fax: 503-774-8236
BuenR@milwaukieoregon.gov
Project Details
The project will improve utilities located along McLoughlin Boulevard and the surrounding area.
Project work includes:
- (January – May) : Abandonment of 12” water line on 99E Highway/ SE McLoughlin Boulevard from SE Milport Road to SE Beta Street and extending the existing 12” water line on SE Main Street from SE Mailwell Drive to SE Beta Street.
- New water line installation is now complete on SE Main Street. Contractor is now patching the trenches. There will still be lane closures where necessary, and delays should still be expected.
-
(January – May) : Upsizing storm sewer pipe on SE Milport Road from 18” to 30” PVC Pipe.
-
New storm sewer pipe has been installed and the contractor is now patching the trenches. Lane closures where necessary, and delays should still be expected
-
-
(February – May) : Realignment of sanitary sewer line on 99E Highway/SE McLoughlin Boulevard from SE Ochoco Street to SE Clatsop Street.
-
The sanitary sewer line has been installed and the contractor is now patching the trenches. Lane closures and delays may still be required.
-
-
(April - May) : Paving and project cleanup.
-
The contractor is working to finish paving, sealing new asphalt, and striping roadways when weather permits. Lane closures and delays should still be expected. Check back for project updates for specific closures.
-
Alerts & Updates
Update: The project is complete. There will be no further traffic impacts as a result of this work.