Dates 
Construction: Spring 2015
Project Status 
Completed
Budget 
$1.2 Million
Contact 

Geoff Nettleton, PE
Civil Engineer
Phone: (503) 786-7609
Fax: (503) 774-8236
Email: nettletong@milwaukieoregon.gov

Project Details

This project will replace aging undersized cast iron storm pipe with new highly durable plastic pipe that will relieve flooding in the project area. This project will also decommission drywells along the project alignment.  The City has hired AKS Engineering and Forestry to perform the survey and design of this project.

 

Alerts & Updates

All work is complete. Project closeout is underway.

Downloads

PDF icon Scope of Work (896 KB)